A schedule runs one test definition against one environment of the same project, on a cron expression, in a time zone you choose.

E2E against production 0 6 * * 1-5 Europe/Vienna skip

Standard five-field cron: minute, hour, day of month, month, day of week.

Expression Runs
0 6 * * * Every day at 06:00
0 6 * * 1-5 Weekdays at 06:00
*/15 * * * * Every 15 minutes
0 * * * * Every hour, on the hour
30 2 1 * * 02:30 on the first of every month

Aliases such as @daily and @hourly work too; @reboot does not. Expressions that can never match, such as 0 0 30 2 *, are refused. The form offers presets and previews the next three run times while you type.

Schedules have minute precision. A run is created within a few seconds after its minute.

The expression is evaluated on the wall clock of the schedule’s time zone (any IANA name, such as Europe/Vienna or America/New_York), so “06:00” stays 06:00 local time across daylight saving changes.

On the two nights a year when the clock changes:

  • Spring forward: a time that does not exist (02:30 when clocks jump from 02:00 to 03:00) runs at the first moment after the gap, 03:00.
  • Fall back: a time that occurs twice runs only the first time.

Every local time runs at most once. A side effect: a schedule that runs every few minutes pauses during the repeated hour, because those local times already ran.

Times are shown in the schedule’s time zone with its abbreviation (Sat 27 Sep 2026, 06:00 CEST); hover for UTC.

What happens when the schedule fires while its previous run is still queued, preparing, or running:

Policy Behaviour
skip (default) No new run. The schedule records the skip, visible on its row.
queue A new run is queued and starts after the previous one finished. At most one run waits: a further tick while one is already waiting is skipped.
allow A new run is created regardless; only the concurrency limits apply.

Only the schedule’s own runs count. A manual or API run of the same suite does not block a schedule.

skip suits most suites: if the 06:00 run is still going at 06:15, another run tests nothing new. queue suits schedules where every slot matters, without letting a hanging suite pile up runs behind it.

If TestFleet was down when slots were due, the schedule creates one run for the oldest missed slot when it is back, then continues with the next regular slot. A schedule every 15 minutes after two hours of downtime creates one catch-up run, not eight. The run page shows both the slot it was scheduled for and when it was actually queued.

A slot never produces two runs, even if several TestFleet processes or ticks race for it.

When a schedule fires for a disabled test definition, it records “skipped because the test definition is disabled” and moves on to its next slot. It resumes by itself when the test definition is enabled again.

  • Each schedule’s row on the project page shows its last outcome: the run it created and its status, or why it skipped.
  • The dashboard lists upcoming schedules and marks one overdue when it is more than 2 minutes late. That only happens when scheduling itself is stuck.
  • An admin can subscribe a notification channel to system.scheduling_stalled, sent when any schedule is more than 10 minutes overdue. See Notifications.
  • For the case TestFleet cannot report itself (the whole server is down), set HEARTBEAT_URL to an external dead man’s switch such as Healthchecks.io. TestFleet pings it after every schedule tick; the external service alerts when the pings stop.